MODIFICATION PROPOSALS--PRICE BREAKDOWN (DEC 1991)
- (a) The Contractor shall furnish a price breakdown, itemized as required and within the time specified by the Contracting Officer, with any proposal for a contract modification.
- (b) The price breakdown—
- (1) Must include sufficient detail to permit an analysis of profit, and of all costs for—
- (i) Material;
- (ii) Labor;
- (iii) Equipment;
- (iv) Subcontracts; and
- (v) Overhead; and
- (2) Must cover all work involved in the modification, whether the work was deleted, added, or changed.
- (1) Must include sufficient detail to permit an analysis of profit, and of all costs for—
- (c) The Contractor shall provide similar price breakdowns to support any amounts claimed for subcontracts.
- (d) The Contractor's proposal shall include a justification for any time extension proposed.
Prescription: 236.101-71 Clauses
As prescribed in 236.101-71(a). Scope applicability here before applying the clause.
- (a) Insert the following clauses in all fixed-price construction solicitations and contracts—
- (1) 252.236-7000, Modification Proposals—Price Breakdown; and
- (2) 252.236-7001, Contract Drawings and Specifications.
Version history
One version on record, first captured 2026-06-11 15:52:28, effective February 1, 2026.
Prescription: 236.101-71
Prescribing text cropped from the same deviation PDF.
Clause text (pages 9–10)
Rendered from the deviation PDF. Open the full PDF.